I am happy to report that our building permit is FINALED! It was Aristotle who said "patience is bitter, but its fruit is sweet." Yeah...I wonder if he endured a creamery build-out, because that pretty much sums up what it is like. Just to recap, we started the permitting process with the County of Marin back in September 2012; they finally issued a building permit to us on January 15th; we were done building the creamery and got licensed by the state of California 40 days later on Feb. 23rd; it took another 60 days after that to wrap up the septic issues in order to get the final blessing from the county; so from permit issuance to permit final, it took exactly 100 days. The County of Marin has lifted all the holds, done their last site inspection, and given their final approval, closing the book on this project once and for all....at least as far as they are concerned. We, on the other hand, still have a long to-do list!

view of the make room, with our new vat and all our cheesemaking stuff
view of the almost-complete whey removal system which is designed to be loaded into a tank for feeting to pigs & other livestock
view into the mechancial room, the door leads into the bathroom
mechanical room, with all of our new systems necessary for the creamery
a big mess of tools are still scattered all around the back of the creamery
the mechanical room window screens are a bit worse for wear after nearly 40 years. We will be repairing this soon.
front of the creamery buidling is looking good with new entry doors, and new windows and grade vents. It needs a coat of paint!
view into what will be a milk room, but we need it for aging cheese since we have nearly 3000 wheels produced this year so far
creamery bathroom is looking much better, but still needs fresh paint and some floor tile
another craigslist find: commercial dishwasher with 3 min wash cycle. We will use this to clean cheese hoops
These sneaky lambs figured out how to escape through an opening on the side of the fence
this black lamb has a very cool color pattern with a white hourglass on her head and a white tail
our complete signed and approval building permit, woohoo!
seana and marissa's picture

Fast & Furious Creamery

It’s been 20 days since we finally got the building permit, and there hasn’t been an idle day since. After all those months of waiting and trying to navigate through red tape and overcome bureaucracy, it’s actually happening. The creamery is really coming to life. The action has been fast and furious as we rush to bring the creamery into a functional state. We are pretty much working at a pace that pushes the limits of our budget, and especially our physical and mental stamina. Our muscles & joints have ached in new and interesting places, and we’ve only sustained minor cuts and bruises. It’s amazing though how the body can be so dead-tired, but the mind keeps racing. Well, mine does anyway. To paraphrase the lyrics of “Gin & Juice,” one of the greatest rap songs of all time: I’ve got my mind on my cheese and my cheese on my mind. Here is a recap of the big accomplishments of the past 20 days…

 

view of vents for floor drains, wood forms for the curbs that will be poured for the new milk room
another view of the drain vents as well as the rebar for the new concrete
a major bargain - we got this sink for $300 from a guy who used to have a BBQ place in Berkeley. It needs some cleaning up.
Dave is removing the worst toilet in Tomales (well, it looked like the worst to me)
here is the clean shiny new low-flow toilet, which Marin County required
The concrete truck is setting up to pour the new floor
Here is Gary, Marissa's dad, lending a helping hand to spread the new concrete around.
New business license for Marin County. I'm annoyed by the fact that they called me Seana "Dalton" -that's not my name.
Framing and doors for new milk room
Dave is boring holes for the new plubming on this "wet wall" where most of the plumbing will run
Here is the plaster crew applying a base glue type product to help seal and fill the old plaster's cracks and holes
These are some of the color options for the new plaster. I chose "Dove Gray"
The plaster crew worked 8 hours straight while Dave worked on plumbing.
Sparks were flying as Dave and I both took turns grinding off old nails and bolts from the walls
Working into the night, Dave finished up the plumbing on this wall
A view into the creamery from the area we call the "nook" which is for dry storage.
A view from the entry way, with Dave checking on his plubming work.
A fair amount of beer has gone into this creamery project. On this evening, it was brews from Deschutes in Oregon.
As you can see, it looks like a construction site!