regulations
Finally FINALED!
April 25, 2013 - 7:23pm | by seana and marissaI am happy to report that our building permit is FINALED! It was Aristotle who said "patience is bitter, but its fruit is sweet." Yeah...I wonder if he endured a creamery build-out, because that pretty much sums up what it is like. Just to recap, we started the permitting process with the County of Marin back in September 2012; they finally issued a building permit to us on January 15th; we were done building the creamery and got licensed by the state of California 40 days later on Feb. 23rd; it took another 60 days after that to wrap up the septic issues in order to get the final blessing from the county; so from permit issuance to permit final, it took exactly 100 days. The County of Marin has lifted all the holds, done their last site inspection, and given their final approval, closing the book on this project once and for all....at least as far as they are concerned. We, on the other hand, still have a long to-do list!